MENASHA, WI (WTAQ-WLUK) — The new Racine Street Bridge in Menasha will open a few months later than originally planned.
The Wisconsin Department of Transportation says the bridge will now open in mid-December. That’s delayed from the original estimate of September. The DOT says parts that go in the raising and lowering mechanism are scheduled for delivery this month, with installation beginning next month.
The bridge connects downtown Menasha with Doty Island across the Fox River.
Meanwhile, the roundabouts at Main and Ahnaip streets will open by late September, compared to the original estimate of late August. The DOT says while construction is mostly complete on the roundabouts, the delivery of supplies for overhead street lighting has been delayed.